PEC, Silverstone

CASE STUDIES

Project Name / PEC, Silverstone

Time limited refurbishment: 9 days

A detailed procurement programme and pre-planning activities by the hour enabled us to deliver this fast-paced, nine-day refurbishment project half a day early.  Detailed planning and close communication with the client were the key to success on this project.

Key Disciplines:  Planning and programming, Floor chasing, Electrical, Partitions, Tiling, Bi-fold doors, Soft flooring, Decorating and Sparkle clean.

Quick Facts

850m2 of floor preparation, membrane and tiles over two floors
Duration: 9 days (24/7 working)
Budget: £200,000
Sector: Leisure
Location: Silverstone

Works carried out:

24/7 x 9 day programme, to achieve a deadline 3 days
before the British Grand Prix

The contract works included strip-out, floor-chasing, installation and modification of electrical circuits, stud partitions, joinery, carpets, vinyl flooring, bi-fold doors, decorating, and floor tiling.

Bromley Hays is a turnkey main contractor that provides a one-stop-shop for building refurbishment projects.

Reliable, professional, easy to work with and solutions-focussed, the Bromley Hays team has a track record of delivering successful construction, refurbishment, fit-out and dilapidation solutions for clients since 2009.